EnergyFeatured NewsNuclear PowerRegulations

NRC SMR Licensing in 2026: Part 53 Is Final, Part 57 Is Next, and the First Advanced Reactors Break Ground

NRC SMR licensing is changing fast: the US regulator has finalised a new framework for advanced reactors, proposed another for microreactors, and issued its first permit for a commercial non-water-cooled plant in more than 40 years.

NRC SMR licensing: the rule changes

The push comes from Executive Order 14300, signed in May 2025. It told the NRC to rewrite its rules within 18 months and to decide new reactor applications within 18 months, as POWER magazine explains.

Designs, permits and projects

  • NuScale: the NRC approved the uprated 77 MWe design, but this was in May 2025, not 2026. A design approval is not a permit to build.
  • TerraPower, Kemmerer (Wyoming): the NRC issued construction permit CPAR-1 on 9 March 2026. It is the first approval for a non-light-water commercial reactor in over 40 years, and the staff review took under 18 months. An operating licence is still required.
  • Kairos Power, Hermes 2 (Tennessee): ground was broken on 17 April 2026. The 50MWe plant is planned to supply the Tennessee Valley Authority and Google data centres.
  • Seadrift (Texas): Dow’s Long Mott Energy and X-energy filed a construction permit application for Xe-100 reactors in March 2025. The NRC is aiming for an 18.5-month review, and no decision has been reported.

A fair reality check

GO-IBR Research Team take

For compliance and regulatory teams, the useful signal is the framework itself. Part 53 and the proposed Part 57 give developers risk-informed, performance-based routes in place of exemption-heavy reviews. Watch whether the NRC meets its own review clocks on TerraPower’s operating licence and the Seadrift permit, because that will show if the reforms hold up in practice.

Last updated 22 October 2026. Sources: POWER magazine; Nuclear Engineering International; American Nuclear Society; US NRC; World Nuclear News; MarketsandMarkets.

By the GO-IBR Research Team. © go-ibr.com